CSLB General Building (B) practice questions
213 free questions with answers and explanations.
- 201.A general contractor is estimating the quantity of 2x4 lumber needed for the top and bottom plates of a 40-foot long wall. The wall will have a single top plate and a single bottom plate. The lumber is sold in 16-foot lengths. How many 16-foot 2x4s are needed, assuming no waste is generated from cutting?Planning and Estimating
- 202.Under Cal/OSHA regulations for fall protection, what is the minimum height above a lower level at which guardrails, safety nets, or personal fall arrest systems are generally required for employees on walking/working surfaces?Safety
- 203.A contractor is estimating the quantity of lumber needed for a wall framing project. The wall is 30 feet long and 8 feet high, with studs spaced 16 inches on center (O.C.). Assuming a top plate, a sole plate, and a double top plate, how many 2x4x8 studs are needed for the wall, NOT including waste or blocking?Planning and Estimating
- 204.A contractor is preparing a bid for a residential addition that includes a new concrete patio. The patio will be 20 feet long, 15 feet wide, and 4 inches thick. If concrete costs $135 per cubic yard, what is the estimated material cost for the patio, rounded to the nearest dollar?Planning and Estimating
- 205.An employer is updating their Hazard Communication Program. Which of the following is NOT one of the primary components required by Cal/OSHA's Hazard Communication Standard (HCS)?Safety
- 206.Which of the following is NOT considered a hazardous material according to Cal/OSHA's Hazard Communication Standard (HCS)?Safety
- 207.A contractor is preparing to use a ladder jack scaffold. Which of the following is a Cal/OSHA requirement for the planks used on this type of scaffold?Safety
- 208.A general contractor is estimating the quantity of plywood needed for the subfloor of a new residential building. The building footprint measures 40 feet by 60 feet. If standard plywood sheets are 4 feet by 8 feet, how many sheets are required, assuming no waste factor for simplicity?Planning and Estimating
- 209.A contractor is reviewing a structural drawing for a new commercial building. The drawing indicates a beam with the designation 'W12x26'. What does the 'W' in this designation typically represent?Planning and Estimating
- 210.A contractor is developing a preliminary schedule for a commercial renovation project. An activity, 'install drywall', cannot start until 'framing inspection passed' is complete. This type of relationship between activities is known as a:Planning and Estimating
- 211.A contractor is planning to pour a concrete driveway that is 60 feet long, 10 feet wide, and 4 inches thick. If concrete is ordered in full cubic yard increments, how many cubic yards of concrete should be ordered to account for standard waste?Planning and Estimating
- 212.A contractor is preparing to use a portable ladder to access a work platform. According to Cal/OSHA, what is the MINIMUM distance that the top of the ladder should extend above the landing surface?Safety
- 213.A general contractor is reviewing the project schedule and notes a task labeled 'Install Drywall' that cannot begin until 'Rough Electrical' and 'Rough Plumbing' are both 100% complete. This is an example of what type of scheduling relationship?Planning and Estimating