Journeyman Plumber ExamDrainage, Waste, and Venting (DWV) SystemsEasy

A plumber is inspecting a newly installed 4-inch building sewer. What is the minimum required size for the cleanout fitting that serves this building sewer, according to most plumbing codes?

  1. A2 inches
  2. B3 inches
  3. C6 inches
  4. D4 inches
Show answer & explanation

Correct answer: D. 4 inches

Plumbing codes generally require cleanouts to be the same size as the pipe they serve, up to a certain maximum. For a 4-inch building sewer, the minimum required cleanout size is 4 inches to allow for proper access and cleaning. However, the maximum is often 4 inches, even for larger building sewers.

Why the other options are wrong

  • A. 2 inches is too small for a 4-inch building sewer, inhibiting effective cleaning.
  • B. 3 inches is also too small for a 4-inch building sewer.
  • C. 6 inches would be unnecessarily large and is not typically required for a 4-inch pipe, though it might be used for larger sewers.

Building Sewer Cleanout Size

The minimum diameter of a cleanout fitting required for a building sewer, generally matching the diameter of the sewer pipe it serves.

  • Provides access for clearing blockages.
  • Must be accessible for rodding tools.
  • Typically the same size as the drain pipe, up to 4 inches.
  • Larger sewers (e.g., 6-inch) often still use 4-inch cleanouts.

Memory trick: Cleanout Size: Match the Pipe, Keep it Tight.