NASCLA Accredited Commercial General ContractorGeneral RequirementsMedium

A commercial general contractor is hired for a project with a fixed completion date. The contract includes a clause stating that for every day the project is delayed beyond this date, the contractor will pay the owner $1,500. This amount is a reasonable pre-estimate of the actual damages the owner would incur. What type of contract clause is this?

  1. ALiquidated Damages Clause
  2. BIndemnification Clause
  3. CForce Majeure Clause
  4. DPenalty Clause
Show answer & explanation

Correct answer: A. Liquidated Damages Clause

A liquidated damages clause specifies a predetermined amount of money that must be paid as damages for a breach of contract (like delayed completion), provided that the amount is a reasonable forecast of the actual damages and not a penalty.

Why the other options are wrong

  • B. An indemnification clause shifts liability for losses generally, not specifically for delays.
  • C. A Force Majeure Clause excuses delays due to unforeseeable events, not defines penalties for avoidable delays.
  • D. A penalty clause is generally unenforceable if the amount is excessive and not a reasonable pre-estimate of actual damages.

Liquidated Damages Clause

A contract provision that specifies a predetermined sum of money that one party will pay the other as compensation for a specific breach of contract (e.g., late completion).

  • Must be a reasonable estimate of actual damages, not a punishment.
  • Aims to avoid difficult calculation of actual damages in court.
  • Common in construction contracts for project delays.

Memory trick: Liquidated damages: a 'liquid' sum for 'late' harm.

More General Requirements questions