NASCLA Accredited Commercial General ContractorGeneral RequirementsEasy

A general contractor is reviewing the project schedule for a new commercial building. The critical path analysis indicates that the foundation work, structural steel erection, and exterior enclosure are sequential activities with no float. If a two-week delay occurs during the foundation work, what is the immediate impact on the project's overall completion date?

  1. AThe project completion date will remain unchanged due to buffer time in other activities.
  2. BThe project completion date will be delayed by more than two weeks due to cascading effects.
  3. CThe project completion date will be accelerated by two weeks if resources are reallocated.
  4. DThe project completion date will be delayed by exactly two weeks.
Show answer & explanation

Correct answer: D. The project completion date will be delayed by exactly two weeks.

Activities on the critical path have zero float. Any delay to a critical path activity directly impacts the project's overall completion date by the exact duration of that delay. Therefore, a two-week delay in foundation work will cause a two-week delay in project completion.

Why the other options are wrong

  • A. Critical path activities have no float, so delays directly affect the end date.
  • B. While cascading effects can occur, the immediate and direct impact of a critical path delay is equal to the delay itself, assuming no other critical paths are affected.
  • C. Delays do not accelerate projects; acceleration requires specific actions like crashing or fast-tracking.

Critical Path

The sequence of project activities that determines the shortest possible duration to complete the project, with no float (or slack) time.

  • Any delay to a critical path activity will delay the entire project.
  • Identified through Critical Path Method (CPM) scheduling.
  • Requires careful monitoring and management to keep projects on schedule.

Memory trick: If the main road is blocked, your arrival is delayed by exactly that block.