PMI CAPM (Certified Associate in Project Management) Examination Content OutlineRisk Management and ComplianceMedium

A project manager is evaluating potential responses for a high-impact, high-probability threat. The team proposes outsourcing a critical component to a specialized vendor who has expertise in mitigating similar risks. Which risk response strategy is being considered?

  1. AMitigate
  2. BAccept
  3. CAvoid
  4. DTransfer
Show answer & explanation

Correct answer: D. Transfer

Transferring a risk involves shifting the impact of a threat, along with ownership of the response, to a third party, such as outsourcing to a specialized vendor.

Why the other options are wrong

  • A. Mitigate involves reducing the probability or impact of a risk, but outsourcing shifts the responsibility, not just reduces it.
  • B. Accept involves acknowledging the risk without taking action, which is not what outsourcing does.
  • C. Avoid involves eliminating the threat entirely, which is not achieved by outsourcing a component.

Risk Transfer

A risk response strategy for threats that involves shifting the impact of a threat to a third party, often through contracts, insurance, or outsourcing.

  • Shifts responsibility and financial impact.
  • Does not eliminate the risk, but moves it.
  • Commonly achieved via insurance, contracts, or outsourcing.

Memory trick: Avoid, Transfer, Mitigate, Accept: ATMA - Always Take More Action!