OSHA 10-Hour Construction ReviewScaffoldsHard

A worker is using an adjustable suspension scaffold. What is the maximum vertical interval between scaffold ties or guying for standard light-duty scaffold frames?

  1. A26 feet
  2. B20 feet
  3. C30 feet
  4. D15 feet
Show answer & explanation

Correct answer: A. 26 feet

For standard light-duty scaffold frames, OSHA requires that the first tie-in be at 4 times the minimum base dimension, and subsequent ties must be at a maximum vertical interval of 26 feet. This ensures stability and prevents overturning.

Why the other options are wrong

  • B. 20 feet is not the specified maximum vertical interval by OSHA for light-duty frames.
  • C. 30 feet exceeds the maximum allowable vertical interval for light-duty scaffold frames.
  • D. 15 feet is too frequent for vertical tie-in intervals for light-duty scaffolds.

Scaffold Tie-In Vertical Interval (Light-Duty)

The maximum vertical distance between points where a scaffold must be tied, braced, or guyed to a structure for stability, specifically for light-duty frames.

  • First tie at 4x base dimension
  • Subsequent ties max 26 feet vertical
  • Ensures scaffold stability

Memory trick: Light-duty, 26 feet, for stability, can't be beat!