Project Management Professional (PMP)® Examination Content OutlinePeopleEasy

A project manager is leading a project nearing its critical delivery deadline. The team has been working long hours, and stress levels are high. The project manager notices a significant drop in team morale and productivity. To address this situation and re-energize the team, which action should the project manager take?

  1. ARemind the team of the consequences of not meeting the deadline to increase motivation.
  2. BOrganize a team-building event focused on relaxation and acknowledging their hard work.
  3. CAssign more challenging tasks to high-performing team members to keep them engaged.
  4. DImplement stricter monitoring of individual tasks to ensure everyone is meeting their commitments.
Show answer & explanation

Correct answer: B. Organize a team-building event focused on relaxation and acknowledging their hard work.

Organizing a team-building event focused on relaxation and acknowledgment is a proactive way to boost morale, reduce stress, and re-energize a fatigued team, directly supporting team performance.

Why the other options are wrong

  • A. Reminding of negative consequences can increase anxiety and decrease motivation, leading to burnout.
  • C. Assigning more challenging tasks during high stress can lead to further burnout and resentment, not re-energizing the team.
  • D. Stricter monitoring can increase stress and decrease trust, further lowering morale.

Support Team Performance

Actions taken by the project manager to foster a positive team environment, boost morale, and enable team members to perform at their best.

  • Involves recognizing efforts and successes.
  • Addresses issues like burnout and low morale.
  • Aims to create a supportive and motivating workplace.

Memory trick: Celebrate effort, alleviate stress, and watch spirits rise.