Praxis Core Academic Skills for Educators: Mathematics (5733)Number and QuantityMedium

A project manager is estimating task durations. Task X is estimated to take between 3.5 and 4.5 hours. Task Y is estimated to take between 2.75 and 3.25 hours. What is the maximum possible combined time, in hours, for both tasks?

  1. A7.75 hours
  2. B7.00 hours
  3. C8.00 hours
  4. D6.25 hours
Show answer & explanation

Correct answer: A. 7.75 hours

To find the maximum possible combined time, you must add the maximum estimated times for each task. Max time for Task X = 4.5 hours. Max time for Task Y = 3.25 hours. Combined maximum time = 4.5 + 3.25 = 7.75 hours.

Why the other options are wrong

  • B. This might come from adding the lower bound of one and the upper bound of the other, or an arithmetic error.
  • C. This might result from an arithmetic error or incorrect rounding.
  • D. This is the minimum combined time (3.5 + 2.75).

Estimation with Ranges

When dealing with quantities defined by ranges (minimum and maximum values), calculations for combined minimums or maximums involve adding the respective bounds.

  • To find maximum combined value, add individual maximums.
  • To find minimum combined value, add individual minimums.
  • This principle applies to addition and subtraction of estimated values.

Memory trick: For max, add the max; for min, add the min. Don't mix 'em in!