A civil engineer is planning a road construction project. The total length of the road is 25.5 miles. If the crew completes 1/3 of the road in the first month and 2/5 of the remaining road in the second month, how many miles of road are still left to be constructed?

  1. A12.75 miles
  2. B8.5 miles
  3. C15.3 miles
  4. D10.2 miles
Show answer & explanation

Correct answer: D. 10.2 miles

First, calculate the length completed in the first month. Then, determine the remaining length. From that remaining length, calculate 2/5 completed in the second month, and finally, subtract that from the remaining length to find what is left.

Why the other options are wrong

  • A. This is the remaining road after the first month, not after both months.
  • B. This is the amount completed in the first month, not the amount remaining.
  • C. This is the amount completed in the second month with respect to the total, not the remaining amount.

Sequential Fractional Changes

Sequential fractional changes involve calculating a fraction of a total, then calculating a fraction of the *remaining* amount. Each step alters the base for the next calculation.

  • Each fraction applies to the current remaining quantity, not the original total.
  • Requires careful step-by-step calculation.
  • Common in resource allocation or consumption problems.

Memory trick: First fraction, then what's left, then another fraction of *that* amount, then what's truly left.