Professional Scrum Master I (PSM I)Scrum Theory & PrinciplesHard
During a Sprint, the Developers discover a significant technical challenge that was not anticipated during Sprint Planning. Addressing this challenge will require more effort than initially estimated and might jeopardize the Sprint Goal. What Scrum Value is most important for the Developers to uphold in this situation?
- AFocus
- BRespect
- CCommitment
- DCourage
Show answer & explanationAnswer & explanation
Correct answer: D. Courage
The Developers face a tough problem that could threaten the Sprint Goal. Upholding 'Courage' means they have the bravery to acknowledge the issue, openly communicate it to the Product Owner and Scrum Master, and propose necessary adaptations, even if it means potentially failing the Sprint Goal as originally conceived or asking for help.
Why the other options are wrong
- A. Focus is about concentrating on the Sprint Goal, but in this situation, blindly focusing might ignore the underlying problem.
- B. Respect is important for team dynamics but not the primary value for addressing a critical, unexpected technical problem.
- C. Commitment is to the Sprint Goal, but courage is needed to address impediments that might impact that commitment.
Scrum Value: Courage
Scrum Team members have the courage to do the right thing and work on tough problems.
- Enables transparency and addressing impediments.
- Important for confronting difficult truths and making difficult decisions.
- Fosters a safe environment for raising issues.
Memory trick: Have the courage to face the monster in the Sprint.