Professional Scrum Master I (PSM I)Scrum Theory & PrinciplesMedium

During a Sprint Review, stakeholders express concern that the Increment demonstrated is not what they expected, despite previously approving the Product Backlog items at a Sprint Planning. The Scrum Team is surprised by this feedback. Which Scrum Value is most clearly lacking in this scenario?

  1. ACommitment
  2. BFocus
  3. COpenness
  4. DRespect
Show answer & explanation

Correct answer: C. Openness

Openness is crucial for effective collaboration and transparency. The surprise indicates a lack of open communication and transparency between the Scrum Team and stakeholders, leading to misalignment.

Why the other options are wrong

  • A. Commitment is about dedicating oneself to achieving goals, but the primary issue here is understanding, not dedication.
  • B. Focus is about concentrating on the work at hand, which doesn't directly address the communication gap.
  • D. Respect is about valuing others, but the immediate problem is a lack of shared understanding, not disrespect.

Scrum Value: Openness

Scrum Team and its stakeholders are open about the work and the challenges with performing the work.

  • Promotes transparency and collaboration.
  • Essential for early detection of issues.
  • Facilitates trust and shared understanding.

Memory trick: Open communication paves the way for clear understanding.