Professional Scrum Master I (PSM I)Scrum Theory & PrinciplesHard

During a Sprint, the Developers discover a significant technical challenge that was not anticipated during Sprint Planning. Addressing this challenge will require more effort than initially estimated and might jeopardize the Sprint Goal. The Scrum Master encourages the Developers to openly discuss the options with the Product Owner and collaboratively decide on the best path forward, even if it means adjusting the Sprint Backlog. Which Scrum Value is the Scrum Master primarily promoting?

  1. ACommitment
  2. BRespect
  3. CFocus
  4. DCourage
Show answer & explanation

Correct answer: D. Courage

It takes courage for Developers to admit they encountered an unforeseen challenge that might jeopardize the Sprint Goal and to openly discuss potentially difficult adjustments with the Product Owner. The Scrum Master is promoting the courage to do the right thing and address tough problems.

Why the other options are wrong

  • A. Commitment is important, but acknowledging a problem that threatens commitment requires courage first.
  • B. Respect is foundational, but the act of confronting a difficult truth falls under courage.
  • C. Focus is on the Sprint Goal, but the immediate need is to address a problem that challenges that focus.

Scrum Value: Courage

The Scrum Team members have the courage to do the right thing, to work on tough problems, and to be open with each other.

  • Enables transparency and addressing difficult issues.
  • Crucial for acknowledging impediments and seeking help.
  • Supports honest feedback and adapting to challenges.

Memory trick: Be brave, speak up, tackle mountains.