Professional Scrum Master I (PSM I)Scrum Theory & PrinciplesMedium

A Scrum Master observes that the Product Owner is frequently absent from Sprint Reviews and is not actively engaging with stakeholders during these events. What is the most significant risk this behavior introduces to the product's development?

  1. AA decline in the overall quality of the 'Done' Increment.
  2. BReduced Developer motivation due to lack of Product Owner presence.
  3. CIncreased likelihood of the Scrum Team missing their Sprint Goals.
  4. DDifficulty in gaining timely feedback and validating the Increment.
Show answer & explanation

Correct answer: D. Difficulty in gaining timely feedback and validating the Increment.

The Sprint Review is a crucial event for inspecting the Increment and adapting the Product Backlog based on stakeholder feedback. A Product Owner's disengagement during this event directly impedes the collection of timely feedback and validation, making it difficult to ensure the product is evolving in the right direction.

Why the other options are wrong

  • A. Quality is primarily determined by the Definition of Done and Developer practices, not directly by Product Owner presence at the Review.
  • B. While possible, lack of feedback is a more direct and critical risk to the product itself.
  • C. Missing Sprint Goals is more related to Sprint Planning and daily work, though lack of feedback can contribute over time.

Sprint Review Purpose

To inspect the Increment and adapt the Product Backlog if needed. It is a working session to gather feedback and collaborate on the next steps.

  • Collaborative working session.
  • Inspects the Increment.
  • Adapts the Product Backlog.
  • Involves the Scrum Team and stakeholders.

Memory trick: Review the work, refine the plan, get feedback, adapt and advance.