CSLB C-46 Solar ContractorPhotovoltaic System InstallationMedium

A solar installer is connecting a new grid-tied string inverter to a residential service panel. The inverter has a maximum continuous output current of 25A. According to NEC 690.8(A)(1), what is the minimum required ampacity for the conductors carrying the inverter's AC output?

  1. A35A
  2. B30A
  3. C25A
  4. D31.25A
Show answer & explanation

Correct answer: D. 31.25A

NEC 690.8(A)(1) requires that PV system circuit conductors be sized to carry a continuous current of not less than 125% of the maximum current. For an inverter with a maximum continuous output current of 25A, the minimum required ampacity is 25A * 1.25 = 31.25A.

Why the other options are wrong

  • A. 35A is higher than the minimum required, which is acceptable but not the minimum.
  • B. 30A is too low; the calculated minimum is 31.25A.
  • C. 25A is the inverter output, not the minimum required ampacity after applying the 125% rule.

NEC 690.8(A)(1) (PV Conductor Sizing)

Requires PV system circuit conductors to have an ampacity of at least 125% of the maximum continuous current they are expected to carry.

  • Applies to both DC and AC PV circuits.
  • Accounts for continuous operation and potential variations in current.
  • Ensures conductors do not overheat, preventing fire hazards and insulation degradation.

Memory trick: For PV wires, multiply by one-point-two-five, to keep the circuit alive!