CSLB C-33 Painting & DecoratingCoating ApplicationHard

A painting contractor is applying a high-build epoxy coating to a concrete floor at a specified dry film thickness (DFT) of 10 mils. The manufacturer's data sheet states the coating has 80% solids by volume. If the contractor applies 160 square feet per gallon, what is the approximate wet film thickness (WFT) being applied?

  1. A10 mils
  2. B8 mils
  3. C16 mils
  4. D12.5 mils
Show answer & explanation

Correct answer: D. 12.5 mils

To calculate WFT from DFT and % Solids by Volume, use the formula: WFT = DFT / (% Solids by Volume). In this case, WFT = 10 mils / 0.80 = 12.5 mils. The coverage rate (160 sq ft/gal) is extraneous information for calculating WFT from DFT.

Why the other options are wrong

  • A. Incorrect. This is the target DFT, not the WFT.
  • B. Incorrect. This would be the DFT if 80% solids were applied at 10 mils WFT (10 * 0.8 = 8).
  • C. Incorrect. This would be the WFT if DFT was 12.8 mils (12.8 / 0.8 = 16) or if 62.5% solids was applied at 10 mils DFT (10 / 0.625 = 16).

Wet Film Thickness (WFT) Calculation

Wet Film Thickness (WFT) is the thickness of a coating immediately after application, calculated by dividing the desired Dry Film Thickness (DFT) by the coating's percent solids by volume.

  • WFT = DFT / (% Solids by Volume).
  • WFT is always greater than or equal to DFT.
  • Measured with a wet film comb/gauge during application.

Memory trick: WFT is DFT divided by solids, a clear path to follow.