CSLB Law & Business ExamBusiness FinancesHard

A contractor estimated a job's labor cost at $18,000, but the actual labor cost recorded through job costing came to $21,600. What is the percentage cost overrun compared to the original estimate?

  1. A12%
  2. B16.7%
  3. C20%
  4. D24%
Show answer & explanation

Correct answer: C. 20%

The cost overrun percentage is calculated as (Actual − Estimate) ÷ Estimate = ($21,600 − $18,000) ÷ $18,000 = $3,600 ÷ $18,000 = 20%. Job costing allows contractors to compare estimated versus actual costs to identify variances and improve future bidding.

Why the other options are wrong

  • A. Does not match the correct variance-to-estimate calculation.
  • B. This would result from dividing the variance by the actual cost instead of the estimate.
  • D. Overstates the overrun percentage beyond the correct calculation.

Job Cost Variance Analysis

Comparing actual job costs to original estimates to measure overruns or savings, expressed as a percentage of the original estimate.

  • Formula: (Actual - Estimate) ÷ Estimate x 100
  • Used to refine future bids and control costs
  • Large variances signal estimating or cost-control problems

Memory trick: Variance is measured against the original estimate, not the actual.

More Business Finances questions