CSLB Law & Business ExamBusiness FinancesHard

A contractor is working on a long-term project with a total contract price of $300,000 and an estimated total cost of $150,000. To date, $90,000 in costs have been incurred. Using the percentage-of-completion method, how much revenue should be recognized so far?

  1. A$150,000
  2. B$180,000
  3. C$90,000
  4. D$210,000
Show answer & explanation

Correct answer: B. $180,000

Percent complete = Costs incurred ÷ Estimated total cost = $90,000 ÷ $150,000 = 60%. Revenue recognized = 60% × $300,000 contract price = $180,000.

Why the other options are wrong

  • A. This equals the total estimated cost, not the revenue based on percent complete.
  • C. This is only the cost incurred, not the revenue recognized under this method.
  • D. This overstates revenue beyond the actual percentage of work completed.

Percentage-of-Completion Method

An accounting method for long-term contracts that recognizes revenue based on the proportion of costs incurred relative to total estimated costs.

  • Percent complete = Costs to date ÷ Total estimated costs
  • Revenue recognized = Percent complete × Total contract price
  • Commonly used for multi-month construction projects

Memory trick: Costs so far divided by total costs tells you how much of the pie is done.

More Business Finances questions