CSLB General Building (B)Finishes and Building EnvelopeMedium

A stucco contractor is installing a weep screed at the base of an exterior wall over a concrete foundation. Per code, what is the minimum clearance required between the bottom of the weep screed and earth (grade)?

  1. A4 inches
  2. B2 inches
  3. C1 inch
  4. D6 inches
Show answer & explanation

Correct answer: A. 4 inches

The CRC/CBC requires a minimum of 4 inches of clearance between the weep screed and earth, and a minimum of 2 inches above paved areas, to prevent moisture wicking into the wall assembly.

Why the other options are wrong

  • B. This is the minimum clearance above paved surfaces, not earth.
  • C. Too small to prevent moisture wicking from soil.
  • D. Exceeds the code minimum; not the required standard.

Weep Screed Clearance

A metal flashing installed at the base of stucco walls to allow moisture drainage; code sets minimum clearances above grade and paving to prevent water intrusion.

  • 4 inches minimum above earth/grade
  • 2 inches minimum above paved surfaces
  • Prevents wicking and rot at wall base

Memory trick: 'Four inches from dirt keeps stucco alert.'