CSLB General Building (B)Framing and CarpentryMedium

A framing crew is installing 23/32-inch plywood subfloor panels over floor joists using 8d common nails per standard prescriptive nailing requirements. What nailing schedule should they follow?

  1. A8 inches on center at edges and field, uniformly
  2. B6 inches on center at edges, 12 inches on center in the field
  3. C12 inches on center at edges, 16 inches on center in the field
  4. D4 inches on center at edges, 8 inches on center in the field
Show answer & explanation

Correct answer: B. 6 inches on center at edges, 12 inches on center in the field

The standard prescriptive nailing schedule for plywood subfloor panels attached with 8d common nails is 6 inches on center along panel edges and 12 inches on center at intermediate (field) supports. This spacing ensures adequate diaphragm and structural performance.

Why the other options are wrong

  • A. Uniform 8-inch spacing does not match the differentiated edge/field pattern required by code.
  • C. This spacing is too wide and does not meet standard prescriptive requirements.
  • D. This tighter spacing is used for higher-demand diaphragms, not standard subfloor nailing.

Subfloor Nailing Schedule

Wood structural panel subfloors are typically fastened with 8d common nails spaced 6 inches on center at panel edges and 12 inches on center at intermediate supports.

  • 6 in o.c. at edges, 12 in o.c. in field is standard
  • 8d common nails are typical for standard subfloor thickness
  • Tighter spacing may be required for diaphragm shear demands

Memory trick: 'Six at the edge, twelve in the middle keeps the floor from a diddle.'