CSLB General Building (B)Site Work, Foundations and ConcreteHard

A contractor is placing a concrete footing and overnight temperatures are forecast to drop below freezing before the concrete has cured. According to standard cold-weather concreting practices (ACI 306), what minimum concrete temperature must be maintained, and for how long, to protect the fresh concrete?

  1. A40°F for at least 48 hours
  2. B32°F for at least 24 hours
  3. C50°F for at least 3 days
  4. D70°F for at least 7 days
Show answer & explanation

Correct answer: C. 50°F for at least 3 days

ACI 306 cold-weather concreting guidelines require that concrete be maintained at a minimum temperature of 50°F for at least the first 3 days after placement (longer for high-strength or thin sections) to ensure adequate hydration and prevent freeze damage before the concrete gains sufficient strength.

Why the other options are wrong

  • A. 40°F for 48 hours does not meet the minimum temperature or duration required by ACI 306.
  • B. 32°F is the freezing point itself and is too low and too short a duration to protect fresh concrete.
  • D. 70°F for 7 days exceeds the minimum standard requirement and is not the baseline rule.

Cold Weather Concrete Protection (ACI 306)

Guidelines requiring fresh concrete to be maintained at a minimum temperature of 50°F for at least 3 days after placement in cold weather to prevent freeze damage and ensure proper hydration.

  • Minimum protected temperature is 50°F
  • Minimum protection period is 3 days for normal structures
  • Longer protection needed for thin sections or high early strength requirements

Memory trick: 'Fifty for three' keeps fresh concrete from freezing before it gains strength.