CSLB C-27 Landscaping ContractorPlanning and EstimatingEasy

A C-27 contractor is estimating the cost for a landscape project that requires 15 cubic yards of topsoil. The supplier charges $40 per cubic yard for topsoil and a flat delivery fee of $150 per order. If the contractor orders all the topsoil at once, what is the total cost for the topsoil and its delivery?

  1. A$550
  2. B$900
  3. C$600
  4. D$750
Show answer & explanation

Correct answer: D. $750

First, calculate the cost of the topsoil (15 cubic yards * $40/cubic yard = $600). Then, add the flat delivery fee ($600 + $150 = $750).

Why the other options are wrong

  • A. This calculation is incorrect; it seems to add the per-yard cost and delivery fee, then multiply by volume ($40+$150)*15 which is wrong.
  • B. This is an incorrect calculation; possibly multiplying total cost by 1.25 or similar error.
  • C. This only accounts for the cost of the topsoil (15 * $40 = $600), excluding delivery.

Material & Delivery Cost

The total expense incurred for purchasing bulk materials and having them transported to the project site, including both unit cost and delivery fees.

  • Delivery fees can be flat or volumetric.
  • Bulk discounts may apply to materials.
  • Crucial for accurate material budgeting.

Memory trick: Material quantity times unit price, then add the delivery fee.