CSLB C-10 Electrical ContractorPlanning and EstimatingEasy

A residential client is planning a new laundry room. The plans specify a 120V, 20A branch circuit to serve a 4.5 kW electric clothes dryer. What is the minimum continuous load percentage that must be applied to the calculated dryer load when sizing the overcurrent protective device (OCPD) for this circuit?

  1. A80%
  2. B150%
  3. C125%
  4. D100%
Show answer & explanation

Correct answer: C. 125%

According to NEC 210.20(A), the OCPD for continuous loads must be sized at not less than 125% of the continuous load. A continuous load is one where the maximum current is expected to continue for 3 hours or more.

Why the other options are wrong

  • A. 80% is incorrect; this percentage is sometimes used for non-continuous loads when applying demand factors, but not for OCPD sizing of continuous loads.
  • B. 150% is incorrect; while some motor loads or specific applications might require higher percentages, the general rule for continuous loads is 125%.
  • D. 100% is incorrect; continuous loads require an OCPD sized at 125% of the load.

Continuous Load OCPD Sizing

Overcurrent protective devices (OCPDs) for continuous loads (expected to operate for 3 hours or more) must be sized at a minimum of 125% of the continuous load's ampere rating.

  • Continuous load: max current for 3+ hours
  • OCPD must be >= 125% of continuous load
  • NEC 210.20(A) and 215.2(A)(1)

Memory trick: Continuous current needs a 'boost' for the breaker.