California First-Year Law Students' Exam (Baby Bar) — MCContractsMedium

A software developer contracts with a client to create a custom application for $10,000, payable upon completion. The contract includes a provision stating that if the developer breaches the contract, the developer agrees to pay the client $500 for each day the project is delayed beyond the agreed-upon deadline. The client's actual damages for a delay are difficult to ascertain beforehand. The project is delayed by 10 days, and the client seeks to enforce the $500 per day clause. What is the most likely legal classification of this clause?

  1. AA forfeiture clause, unenforceable as it deprives the developer of the benefit of the bargain.
  2. BA penalty clause, unenforceable because the amount is disproportionate to potential actual damages.
  3. CAn acceleration clause, enforceable as it makes the entire debt due upon a single breach.
  4. DA liquidated damages clause, enforceable because the amount is a reasonable pre-estimate of difficult-to-ascertain damages.
Show answer & explanation

Correct answer: D. A liquidated damages clause, enforceable because the amount is a reasonable pre-estimate of difficult-to-ascertain damages.

A clause specifying damages for breach is enforceable as liquidated damages if actual damages are difficult to ascertain at the time of contracting, and the stipulated amount is a reasonable forecast of the likely damages. Here, $500 per day for a custom software delay is likely reasonable.

Why the other options are wrong

  • A. A forfeiture clause typically relates to the loss of a right or property due to failure to perform, not a fixed sum for delay.
  • B. A penalty clause is unenforceable, but this requires the amount to be disproportionate, which is not clearly the case here given the difficulty of ascertaining actual damages for custom software delays.
  • C. An acceleration clause makes the entire remaining balance of a debt due immediately upon a default, which is not what this clause does.

Liquidated Damages Clause

A contractual provision that specifies a predetermined sum of money that must be paid as damages by a breaching party. It is enforceable if actual damages are difficult to ascertain and the stipulated amount is a reasonable forecast of the damages.

  • Purpose is to avoid litigation over damage calculations.
  • Must not be a penalty; must be a reasonable estimate.
  • Enforceability determined at time of contract formation, not breach.

Memory trick: Forecast or Punish? That's the Damages Question.

More Contracts questions