CSLB C-33 Painting & DecoratingBusiness and Project ManagementHard

A painting contractor is managing a project where a key supplier unexpectedly delays the delivery of a specialized primer, potentially impacting the project's completion date. To mitigate this risk, what is the most appropriate step for the contractor to take NEXT?

  1. AImmediately inform the client that the project will be delayed indefinitely.
  2. BCancel the existing order with the supplier and demand a refund.
  3. CIdentify alternative suppliers or methods to acquire the necessary primer and update the schedule.
  4. DWait for the supplier to provide a new delivery date before taking any action.
Show answer & explanation

Correct answer: C. Identify alternative suppliers or methods to acquire the necessary primer and update the schedule.

When facing a supply chain disruption, the most proactive and effective step is to identify alternative solutions (suppliers, products, or methods) to minimize the impact on the project schedule. This demonstrates effective risk management and problem-solving.

Why the other options are wrong

  • A. This is premature and unprofessional; mitigation efforts should precede such an announcement.
  • B. Canceling without an alternative plan could exacerbate the problem and incur additional costs.
  • D. Waiting passively allows the delay to worsen and does not demonstrate effective project management.

Project Risk Mitigation

Actions taken to reduce the likelihood or impact of potential negative events on a project's objectives.

  • Involves identifying, assessing, and responding to risks.
  • Focuses on proactive problem-solving.
  • Aims to keep projects on schedule and budget.

Memory trick: When supply chains snap, seek a new path fast.