ISC2 CISSP (Certified Information Systems Security Professional)Security and Risk ManagementEasy

An airline's critical flight control system experiences a complete outage due to a regional power grid failure. The system's disaster recovery plan specifies that operations must be restored within 24 hours to maintain flight schedules and passenger safety. This 24-hour target represents which of the following?

  1. ARecovery Time Objective (RTO)
  2. BRecovery Point Objective (RPO)
  3. CWork Recovery Time (WRT)
  4. DMean Time To Recover (MTTR)
Show answer & explanation

Correct answer: A. Recovery Time Objective (RTO)

The 24-hour target specifies the maximum acceptable duration for restoring operations after a disaster. This is the definition of the Recovery Time Objective (RTO).

Why the other options are wrong

  • B. RPO defines the maximum acceptable amount of data loss.
  • C. WRT is the time required to configure a recovered system and make it fully operational after RTO.
  • D. MTTR is the average time taken to repair a failed system.

Recovery Time Objective (RTO)

The maximum acceptable duration of time that a system can be down after a disaster or disruption.

  • Determined by business impact analysis (BIA).
  • Measure of desired system availability post-incident.
  • Often dictated by regulatory or contractual obligations.

Memory trick: RPO is point, RTO is time; how much loss, how long till fine.