ISACA Certified Information Systems Auditor (CISA) ExamDomain 4: Information Systems Operations and Business ResilienceHard

An IS auditor is assessing the organization's release management process. The auditor notes that new software releases are often deployed directly into the production environment without a formal 'go/no-go' decision point involving key business stakeholders. Instead, IT operations make the final deployment decision based primarily on technical readiness. What is the MOST significant risk introduced by this practice?

  1. ADifficulty in tracking release versions and configurations.
  2. BDeployment of releases that do not align with current business needs or priorities.
  3. CIncreased burden on the IT operations team to manage deployments.
  4. DReduced ability to perform rollbacks in case of deployment failure.
Show answer & explanation

Correct answer: B. Deployment of releases that do not align with current business needs or priorities.

A 'go/no-go' decision point involving business stakeholders ensures that a release is not only technically ready but also aligns with the business's current strategic objectives, operational readiness, and risk tolerance. Bypassing this step risks deploying software that, while technically sound, may not deliver expected business value or could disrupt critical business processes, thereby failing to meet business needs.

Why the other options are wrong

  • A. Version tracking is part of configuration management, which is distinct from the 'go/no-go' decision.
  • C. While IT operations manage deployments, the risk here is about business misalignment, not just workload.
  • D. Rollback capability is a technical aspect of deployment, not directly related to the business decision to deploy.

Release Go/No-Go Decision

A formal checkpoint in the release management process where key business and IT stakeholders collectively decide whether a new software release is ready for deployment to production, considering technical, operational, and business readiness.

  • Ensures alignment with business objectives.
  • Considers operational readiness and risk tolerance.
  • Involves cross-functional stakeholders.

Memory trick: No business 'go' means the software might just be for show.