Bar Exam — MBE (Multistate Bar Exam)ContractsHard

A homeowner hired a contractor to remodel her kitchen for $20,000. The contract specified that the contractor would use 'Brand X' cabinets. Midway through the project, Brand X cabinets became unavailable due to a supply chain disruption. The contractor, without consulting the homeowner, substituted 'Brand Y' cabinets, which were of similar quality and cost. The homeowner was unaware of the substitution until the project was completed. Upon discovery, the homeowner was furious and demanded that the contractor remove the Brand Y cabinets and install Brand X, or pay for the difference in aesthetic value she perceived, which was significant to her. What is the likely legal outcome regarding the homeowner's demand?

  1. AThe homeowner can demand removal and replacement with Brand X cabinets, as the contractor materially breached the contract.
  2. BThe homeowner can only recover nominal damages, as the substitution did not result in actual financial loss.
  3. CThe homeowner is not entitled to any remedy, as Brand Y cabinets were of similar quality and cost, constituting substantial performance.
  4. DThe homeowner can recover damages for the difference in value between Brand X and Brand Y cabinets, but not demand replacement.
Show answer & explanation

Correct answer: D. The homeowner can recover damages for the difference in value between Brand X and Brand Y cabinets, but not demand replacement.

This scenario involves substantial performance and damages. For construction contracts, if a breach is not material (i.e., there is substantial performance), the non-breaching party is limited to damages. Here, the contractor substantially performed by completing the kitchen with cabinets of similar quality. While the substitution was a breach, it likely does not rise to the level of a material breach requiring complete re-performance, especially if the cost of 'undoing' the work is disproportionate to the harm. The homeowner's remedy would be the difference in value between the promised Brand X cabinets and the installed Brand Y cabinets, reflecting her actual loss, including aesthetic value if proven.

Why the other options are wrong

  • A. Demanding removal and replacement would likely be considered economic waste if the value difference is small compared to the cost of demolition and reinstallation, especially given substantial performance.
  • B. If there's a measurable difference in aesthetic or market value, even if Brand Y was of 'similar quality' in terms of durability, the damages would be more than nominal.
  • C. Even with substantial performance, there is still a breach, and the non-breaching party is entitled to damages for the non-conformity.

Substantial Performance (Common Law)

When a party has performed most of its contractual obligations, but there is a minor, non-material breach. The non-breaching party is not excused from performance but may sue for damages for the minor breach.

  • Applies to common law contracts (services, construction).
  • Prevents forfeiture when performance is nearly complete.
  • Breaching party gets contract price minus damages for the defect.
  • If the breach is material, substantial performance does not apply, and the non-breaching party can treat the contract as discharged.

Memory trick: Performance counts, but perfection's not always required!

More Contracts questions