A technician is preparing to work on a 480V motor control center. Which of the following is the LAST step to verify the absence of voltage AFTER applying lockout/tagout devices?

  1. ANotify all affected personnel that the equipment is de-energized.
  2. BUse a properly rated voltage tester to confirm zero voltage on all phases and ground.
  3. CAttempt to start the equipment to confirm it does not energize.
  4. DVisually inspect all lockout/tagout devices for proper placement.
Show answer & explanation

Correct answer: B. Use a properly rated voltage tester to confirm zero voltage on all phases and ground.

After applying lockout/tagout devices, the final and most critical step before starting work is to verify the absence of voltage using a properly rated and tested voltage detector. This ensures the circuit is truly de-energized and safe to work on.

Why the other options are wrong

  • A. Notifying personnel occurs after lockout/tagout and testing, but before starting work; the question asks about verifying absence of voltage AFTER LOTO.
  • C. Attempting to start the equipment is an early step in the LOTO procedure, before verifying zero voltage.
  • D. Visual inspection of LOTO devices is an important step, but it precedes the actual verification of zero voltage.

Absence of Voltage Verification

The final confirmation using a test instrument that an electrical circuit or equipment is de-energized after lockout/tagout procedures have been applied.

  • Must use a properly rated and tested voltage detector.
  • Check all phases, conductors, and ground points.
  • Performed immediately before beginning work on the equipment.

Memory trick: Always Start The Process, Isolate, Lock, Test, Then Work Safely.