Journeyman Electrician Exam (NEC)Equipment and DevicesHard

A journeyman electrician is calculating the minimum required feeder size for a commercial kitchen with multiple 120-volt, 20-ampere general-purpose receptacle branch circuits. According to the National Electrical Code, what is the demand factor that can be applied to the portion of the receptacle load exceeding 10 kVA for a non-dwelling unit?

  1. A100%
  2. B80%
  3. C75%
  4. D50%
Show answer & explanation

Correct answer: D. 50%

According to NEC 220.42(B) for non-dwelling units, the demand factor for general-purpose receptacle loads is 100% for the first 10 kVA, and 50% for the remainder over 10 kVA. This allows for a reduction in the calculated load for the feeder since not all receptacles will be used simultaneously at full capacity.

Why the other options are wrong

  • A. This is applied to the first 10 kVA of the load, not the portion exceeding 10 kVA.
  • B. This is typically a continuous load derating factor, not a general receptacle demand factor.
  • C. This demand factor is not specified for general-purpose receptacles in non-dwelling units in this context.

Receptacle Demand Load (Non-Dwelling)

For non-dwelling units, the demand load for general-purpose receptacles is calculated using a demand factor of 100% for the first 10 kVA, and 50% for the load exceeding 10 kVA, as per NEC 220.42(B).

  • NEC 220.42(B) applies to non-dwelling units.
  • First 10 kVA of receptacle load is at 100% demand.
  • Load exceeding 10 kVA is at 50% demand.
  • This reduces the calculated load for feeder and service sizing.

Memory trick: Commercial plugs: first 10k is full, rest is half.