NASCLA Accredited Commercial General ContractorSite WorkMedium

A site superintendent is reviewing plans for a new commercial parking lot. The design specifies that the finished grade of the parking lot must have a minimum slope of 1.5% for proper drainage. If the parking lot is 200 feet long in the direction of the slope, what is the minimum required elevation change from one end to the other?

  1. A3.0 feet
  2. B30.0 feet
  3. C1.5 feet
  4. D0.3 feet
Show answer & explanation

Correct answer: A. 3.0 feet

Slope percentage is calculated as (rise / run) * 100. To find the rise (elevation change), rearrange the formula: Rise = (Slope % / 100) * Run. So, Rise = (1.5 / 100) * 200 feet = 0.015 * 200 feet = 3.0 feet.

Why the other options are wrong

  • B. This would be a 15% slope, which is too steep for a parking lot. (30/200)*100 = 15%
  • C. This would be a 0.75% slope, which is too low. (1.5/200)*100 = 0.75%
  • D. This would be a 0.15% slope, which is too low. (0.3/200)*100 = 0.15%

Slope Calculation (Percentage)

Slope percentage is a measure of the steepness of a surface, expressed as the ratio of vertical rise to horizontal run, multiplied by 100.

  • Formula: Slope % = (Rise / Run) * 100.
  • Used in grading for drainage, accessibility, and aesthetics.
  • Expressed as a percentage (e.g., 2%).

Memory trick: Rise over Run, Times a Hundred, That's Your Slope.