Journeyman Plumber ExamPlumbing Code and RegulationsMedium

A plumber is preparing to perform a hydrostatic test on a newly installed sanitary drainage system in a multi-story commercial building. According to the International Plumbing Code (IPC), how long must the water be retained in the system for the test to be considered complete?

  1. A15 minutes
  2. B5 minutes
  3. C10 minutes
  4. D30 minutes
Show answer & explanation

Correct answer: A. 15 minutes

The IPC specifies that a hydrostatic test on a drainage system must hold water for a minimum of 15 minutes without any visible leaks. This duration allows sufficient time for any potential leaks to manifest under pressure.

Why the other options are wrong

  • B. 5 minutes is typically too short for a reliable hydrostatic test on a drainage system.
  • C. 10 minutes is often used for other types of tests, but not the standard for drainage system hydrostatic tests.
  • D. 30 minutes would also pass the test but is longer than the minimum required, potentially wasting time.

Drainage System Hydrostatic Test Duration

The minimum time required for a newly installed drainage system to hold water without leaks during a hydrostatic pressure test.

  • Ensures integrity of joints and pipes.
  • Mandatory inspection requirement.
  • Specific duration set by code.

Memory trick: Drainage test, hydrostatic hold, for fifteen minutes, stories told.