CSLB C-27 Landscaping ContractorSite Preparation and DrainageHard

A C-27 contractor is preparing a subgrade for a new gravel pathway that will experience moderate foot traffic. To ensure long-term stability and prevent settling, what is the generally recommended minimum compaction level for the subgrade in terms of Modified Proctor density?

  1. A95% Modified Proctor
  2. B80% Modified Proctor
  3. C85% Modified Proctor
  4. D90% Modified Proctor
Show answer & explanation

Correct answer: A. 95% Modified Proctor

For subgrades supporting pathways, patios, or other hardscapes, especially those experiencing foot traffic, a minimum compaction level of 95% Modified Proctor density is generally recommended. This ensures sufficient bearing capacity, minimizes settlement, and provides a stable base for the overlying materials, preventing future dips and uneven surfaces.

Why the other options are wrong

  • B. 80% Modified Proctor is typically too low for any structural subgrade and would lead to significant settlement.
  • C. 85% Modified Proctor is also generally insufficient for hardscape subgrades and would likely result in long-term settlement.
  • D. 90% Modified Proctor might be acceptable for some non-critical landscape areas, but 95% is the standard for reliable hardscape bases.

Subgrade Compaction (Hardscape)

The process of densifying the existing ground (subgrade) beneath a hardscape element to achieve a specific density, typically measured by Modified Proctor.

  • Essential for hardscape stability.
  • Prevents future settlement and uneven surfaces.
  • Minimum 95% Modified Proctor density is standard.
  • Achieved through mechanical means (e.g., plate compactor).

Memory trick: Ninety-Five's the Number, No Niggles, No Nosedives.

More Site Preparation and Drainage questions