Commercial Building Inspector B2Public Safety and Special ConstructionHard

A contractor is performing demolition work on an existing two-story commercial building. The demolition involves removing structural elements. According to IBC 3303.1, which of the following is REQUIRED before any structural demolition begins?

  1. AInstallation of temporary shoring and bracing at all building perimeters.
  2. BA certified asbestos survey.
  3. CNotification to the local fire department 24 hours in advance.
  4. DA detailed demolition plan submitted to and approved by the building official.
Show answer & explanation

Correct answer: D. A detailed demolition plan submitted to and approved by the building official.

IBC 3303.1 mandates that before demolition of a building or structure, a demolition plan shall be submitted to and approved by the building official. This plan outlines the procedures and safeguards for the demolition process.

Why the other options are wrong

  • A. Temporary shoring and bracing are part of the *execution* of the demolition plan, not a prerequisite for *beginning* structural demolition; the plan must be approved first.
  • B. While an asbestos survey is often required, it's typically an environmental regulation, not specifically a building code requirement for the demolition process itself, though it may be a prerequisite for permitting.
  • C. Notification to the fire department may be required by local ordinances or for specific hazards, but it's not the universal *building code* prerequisite for *structural* demolition.

Demolition Plan Requirement

Before structural demolition of a building or structure can commence, a comprehensive demolition plan must be submitted to and approved by the building official, detailing the procedures and safety measures.

  • Mandated by IBC 3303.1 for all structural demolition.
  • Ensures worker and public safety.
  • Covers sequence of operations, equipment, and protection measures.
  • Approval is a prerequisite for obtaining a demolition permit.

Memory trick: Before the wrecking ball swings, a plan the official brings.