A contractor is performing demolition work on a portion of an existing six-story commercial building. The demolition involves removing non-load-bearing interior partitions on the third floor. Which of the following is NOT typically required to be submitted to the building official for this type of demolition work?
- AShoring and bracing plan
- BDemolition plan
- CMethod of demolition
- DDust control plan
Show answer & explanationAnswer & explanation
Correct answer: A. Shoring and bracing plan
While shoring and bracing plans are critical for demolition involving structural elements or adjacent structures, removing non-load-bearing interior partitions on a single floor is unlikely to require a detailed shoring and bracing plan to be submitted to the building official. Demolition plans, methods, and dust control are standard requirements for most demolition projects.
Why the other options are wrong
- B. A demolition plan outlining the scope and sequence of work is almost always required.
- C. The method of demolition is crucial for safety and environmental concerns and is typically required.
- D. Dust control is a vital public safety and environmental concern during demolition and is usually required.
Demolition Plan Scope
Demolition plans submitted to the building official detail the scope, methods, and safety procedures for removal of building elements. The level of detail, particularly for structural components, dictates specific requirements like shoring plans.
- Required for most demolition activities.
- Content varies based on demolition complexity.
- Shoring/bracing plans are for structural or complex demolitions.
Memory trick: Demolition: Plan it, show the Method, control the Dust, but only Brace if it's structural.