Residential Building Inspector B1General Administration, Legal, and EnforcementMedium

A property owner is constructing a new single-family dwelling. After the foundation inspection passes, the owner decides to modify the floor plan by adding a bay window extension to the living room, which was not shown on the approved plans. What action is required before proceeding with framing the new bay window?

  1. AThe owner must notify the building official and submit revised plans for approval.
  2. BThe owner needs only to ensure the modification meets setback requirements.
  3. CThe owner may proceed, as minor changes do not require re-approval.
  4. DThe owner must wait for the rough framing inspection to mention the change to the inspector.
Show answer & explanation

Correct answer: A. The owner must notify the building official and submit revised plans for approval.

Any deviation from the approved construction documents, even what seems like a minor change, requires submission of revised plans to the building official for review and approval to ensure continued compliance with the code.

Why the other options are wrong

  • B. Setbacks are important, but not the only concern. Structural, energy, and other code requirements must also be met, which requires plan review.
  • C. No, even minor structural or footprint changes require approval to ensure code compliance.
  • D. Waiting until an inspection is too late; approval must be obtained beforehand.

Approved Construction Documents

Plans, specifications, and other data submitted for permitting and approved by the building official, serving as the basis for construction.

  • Construction must conform to these documents.
  • Changes require resubmission and re-approval.
  • Form the basis for inspections.

Memory trick: Approved plans are like a contract; any change needs a new agreement.