Residential Building Inspector B1General Administration, Legal, and EnforcementMedium
A property owner is constructing a new single-family dwelling. After the foundation inspection passes, the owner decides to modify the floor plan by adding a bay window extension to the living room, which was not shown on the approved plans. What action is required before proceeding with framing the new bay window?
- AThe owner must notify the building official and submit revised plans for approval.
- BThe owner needs only to ensure the modification meets setback requirements.
- CThe owner may proceed, as minor changes do not require re-approval.
- DThe owner must wait for the rough framing inspection to mention the change to the inspector.
Show answer & explanationAnswer & explanation
Correct answer: A. The owner must notify the building official and submit revised plans for approval.
Any deviation from the approved construction documents, even what seems like a minor change, requires submission of revised plans to the building official for review and approval to ensure continued compliance with the code.
Why the other options are wrong
- B. Setbacks are important, but not the only concern. Structural, energy, and other code requirements must also be met, which requires plan review.
- C. No, even minor structural or footprint changes require approval to ensure code compliance.
- D. Waiting until an inspection is too late; approval must be obtained beforehand.
Approved Construction Documents
Plans, specifications, and other data submitted for permitting and approved by the building official, serving as the basis for construction.
- Construction must conform to these documents.
- Changes require resubmission and re-approval.
- Form the basis for inspections.
Memory trick: Approved plans are like a contract; any change needs a new agreement.