Residential Building Inspector B1General Administration, Legal, and EnforcementEasy

A homeowner has completed a new deck addition without obtaining the required building permit. An inspector discovers this during a routine neighborhood inspection. What is the most appropriate initial action the inspector should take regarding this violation?

  1. AAdvise the homeowner that no action is necessary if the deck appears structurally sound.
  2. BImmediately issue a stop work order and require the deck to be demolished.
  3. CSchedule a final inspection to determine if the deck meets code requirements.
  4. DIssue a notice of violation and inform the homeowner of the permit application process.
Show answer & explanation

Correct answer: D. Issue a notice of violation and inform the homeowner of the permit application process.

When construction is performed without a permit, the initial step is to issue a notice of violation and guide the homeowner on how to rectify the situation by applying for the necessary permits and subsequent inspections.

Why the other options are wrong

  • A. Unpermitted work, regardless of apparent quality, is a violation and requires official action.
  • B. Demolition is typically a last resort after other remedies have failed or if the structure is demonstrably unsafe.
  • C. A final inspection cannot be performed without a permit being issued and prior required inspections being completed.

Unpermitted Work

Construction or alteration performed without obtaining the required building permits from the local jurisdiction.

  • Requires a notice of violation.
  • Owner must apply for retroactive permits.
  • Subject to fees and potential penalties.

Memory trick: Unpermitted work always starts with a warning and a path to proper paperwork.