Residential Building Inspector B1General Administration, Legal, and EnforcementMedium

A building permit was issued for a new residential addition, and construction began shortly after. During the framing inspection, the inspector notices that the contractor has not posted the permit card in a conspicuous location on the job site, as required by local ordinance. What is the most appropriate action for the inspector to take?

  1. AImmediately issue a stop work order until the permit card is posted.
  2. BFail the inspection and require the contractor to reschedule once posted.
  3. CIgnore the oversight, as it does not directly impact structural integrity.
  4. DInform the contractor of the requirement and instruct them to post it immediately.
Show answer & explanation

Correct answer: D. Inform the contractor of the requirement and instruct them to post it immediately.

While posting the permit card is a requirement, its absence is typically a minor administrative violation. The most appropriate initial action is to inform the contractor and require immediate compliance, rather than issuing a stop work order or failing the entire inspection for this administrative detail.

Why the other options are wrong

  • A. A stop work order is too severe for a missing permit card, unless there are other, more serious violations.
  • B. Failing the inspection for this alone is disproportionate; it can usually be corrected on the spot.
  • C. Ignoring the requirement is not an option; it's a code or ordinance provision that must be enforced.

Permit Card Posting

Requirement for the approved building permit or a copy thereof to be conspicuously displayed on the job site for easy access by the building official and public.

  • Mandated by local ordinances.
  • Facilitates inspection verification.
  • Administrative requirement, not typically a critical safety issue.

Memory trick: Missing permit card is a quick fix, not a show-stopper.