CompTIA Project+ (PK0-005)Tools and DocumentationEasy

A project manager is leading a project where the team is co-located, and daily face-to-face updates are feasible. The team needs a quick, visual way to track the progress of their current sprint, specifically focusing on the amount of work remaining. Which tool is most appropriate for their daily stand-up meetings?

  1. ARACI matrix
  2. BBurndown chart
  3. CWork Breakdown Structure (WBS)
  4. DGantt chart
Show answer & explanation

Correct answer: B. Burndown chart

A burndown chart is an Agile tool specifically designed to visually represent the amount of work remaining in a sprint over time. It's ideal for daily stand-ups to quickly assess progress and identify potential issues.

Why the other options are wrong

  • A. A RACI matrix defines roles and responsibilities, not sprint progress.
  • C. A WBS decomposes project work, not tracks daily sprint progress.
  • D. A Gantt chart is for detailed project scheduling, not a quick daily update on remaining sprint work.

Burndown Chart

A visual representation of the work remaining versus time in an Agile project. It tracks progress during a sprint or iteration, showing how much work is left and helping predict if the team is on track to complete the sprint goals.

  • Shows remaining work over time.
  • Used in Agile methodologies (e.g., Scrum).
  • Helps identify if a team is ahead, behind, or on track.
  • Commonly reviewed during daily stand-up meetings.

Memory trick: Burndown drops, RACI defines, Gantt plans, WBS breaks.