CompTIA Project+ (PK0-005)Tools and DocumentationMedium

A project manager is preparing to conduct a lessons learned session at the end of a project. To ensure all key insights, successes, and challenges are captured systematically, and to provide a reference for future projects, which type of project documentation should be created?

  1. AStakeholder register
  2. BProject charter
  3. CChange log
  4. DLessons learned register/report
Show answer & explanation

Correct answer: D. Lessons learned register/report

A lessons learned register or report is the specific project documentation tool used at the end of a project (or phase) to systematically capture and document knowledge gained, including successes, failures, and recommendations for future projects.

Why the other options are wrong

  • A. A stakeholder register identifies project stakeholders, not lessons learned from the project's execution.
  • B. A project charter is created at the beginning of a project to formally authorize it, not at the end to capture lessons.
  • C. A change log tracks changes made during the project, not the overall lessons learned from its completion.

Lessons Learned Register/Report

A formal document or repository that captures knowledge gained throughout a project, detailing successes, failures, and recommendations for improving future projects or organizational processes.

  • Created during or at the end of a project/phase.
  • Includes what went well, what could be improved, and best practices.
  • Serves as an organizational asset for continuous improvement.
  • Often reviewed at project closure meetings.

Memory trick: Lessons learned remembers, Charter starts, Stakeholder identifies, Change logs track.