CompTIA Security+ (SY0-701)Security ArchitectureHard

A financial services firm requires that, in the event of a regional data center outage, transaction processing must resume within 15 minutes with almost no data loss. Which disaster recovery site strategy BEST meets this requirement?

  1. AA cold site with backup tapes shipped weekly
  2. BA reciprocal agreement with a partner company's data center
  3. CA hot site with real-time data replication and standby active systems
  4. DA warm site with backups restored every 24 hours
Show answer & explanation

Correct answer: C. A hot site with real-time data replication and standby active systems

A very short RTO (15 minutes) with near-zero data loss requires a hot site that maintains real-time (or near-real-time) replicated data and fully running standby systems ready to take over almost immediately.

Why the other options are wrong

  • A. A cold site has no active systems and would take days to become operational, far exceeding 15 minutes.
  • B. A reciprocal agreement depends on another organization's availability and typically cannot guarantee this speed or data currency.
  • D. A warm site with 24-hour-old backups would cause significant data loss and a longer recovery time.

Hot Site

A fully equipped, continuously running alternate processing facility with real-time or near-real-time data replication, enabling near-immediate failover during a disaster.

  • Fastest RTO among site types but most expensive to maintain
  • Warm sites have partial readiness and periodic data sync (higher RPO)
  • Cold sites have infrastructure only, requiring days/weeks to activate

Memory trick: 'Hot means ready right now; cold means start from scratch.'