CSLB Law & Business ExamPublic WorksHard

An awarding body discovers that a subcontractor on a public works project has repeatedly failed to submit certified payroll records despite multiple requests. What action is the awarding body authorized to take under Labor Code §1771.5?

  1. ARequire the subcontractor to re-bid the remaining portion of the work
  2. BImmediately terminate the prime contractor's license
  3. CFile a criminal complaint against the subcontractor with the district attorney
  4. DWithhold contract payments due to the prime contractor until compliance is achieved
Show answer & explanation

Correct answer: D. Withhold contract payments due to the prime contractor until compliance is achieved

Under Labor Code §1771.5 and related provisions, an awarding body may withhold contract payments as a penalty and to secure compliance when a contractor or subcontractor fails to submit required certified payroll records. The awarding body has no authority to revoke a contractor's license or bring criminal charges directly.

Why the other options are wrong

  • A. Re-bidding is not a remedy tied to certified payroll noncompliance.
  • B. Only CSLB can suspend or revoke a contractor's license, not the awarding body.
  • C. Failure to submit payroll records is a civil compliance issue, not a matter for criminal referral by the awarding body.

Withholding for Payroll Noncompliance

Awarding bodies may withhold contract payments from a contractor when certified payroll records are not properly submitted, as authorized by Labor Code §1771.5 and §1776.

  • Withholding applies to the prime contractor even for subcontractor noncompliance
  • Payments are released once records are properly furnished
  • This is a civil enforcement tool, not license discipline

Memory trick: No payroll, no payout.