A property owner records a valid Notice of Completion 10 days after the work of improvement is finished. A subcontractor who is not the direct contractor must now record any mechanics lien within how many days after the Notice of Completion is recorded?

  1. A90 days
  2. B30 days
  3. C60 days
  4. D15 days
Show answer & explanation

Correct answer: B. 30 days

When a valid Notice of Completion (or Cessation) is timely recorded, all claimants other than the direct contractor must record a mechanics lien within 30 days after recording. The direct contractor gets 60 days. Without a recorded Notice of Completion, the default deadline for everyone reverts to 90 days after actual completion.

Why the other options are wrong

  • A. 90 days applies only when no Notice of Completion/Cessation is recorded.
  • C. 60 days applies to the direct contractor, not subcontractors.
  • D. 15 days is not a recognized statutory deadline.

Effect of Notice of Completion on Lien Deadlines

Recording a valid Notice of Completion shortens mechanics lien filing deadlines to 60 days for the direct contractor and 30 days for all other claimants, measured from the recording date.

  • Notice of Completion must be recorded within 15 days after actual completion to be valid
  • Shortens the default 90-day deadline significantly
  • Owners use it to speed up clearing of potential lien claims

Memory trick: NOC recorded: contractor gets 60, everyone else gets 30.